Case 1 – Green Pea Processing Plant

worker checking guages

Roquette/Hatch

Scope

The scope of work that Shreem undertook for this project included the onsite installation of instruments, supply some of the instruments added on the scope, QA/QC instrumentation, QA/QC for instrument installation, Field tubing from manifold to instruments.

Overview

Shreem was selected as a sub contractor for Flour workshop area, Water treatment plant and Utility/Boiler, Natural gas line area for majority of instruments installed onsite.

Services

Construction Management, Procurement, Installation, QA/QC, Project management